Question 1

How do Product Owners typically organize items in the Backlog?



Correct

Question 2

Fill in the blank: As a Product Owner writing a user story, you want every task to have a clear Definition of Done. A clear Definition of Done helps the team better understand how much effort it will take to complete an item. Including a Definition of Done in a user story makes it _____, one of the I.N.V.E.S.T. story-writing criteria.



Correct
Question 3

As a Product Owner, you need to add estimates to your Backlog items. You and your team have over 100 items to estimate and less than one hour to do it. Because of the time limit, you need a technique that will help your team quickly sort items by complexity. Which effort estimation technique should you use?



Correct
Question 4

Which of the following typically happens during a Sprint? Select all that apply.



Correct
Correct
Correct
Question 5

Which of the following may indicate a task meets the Definition of Done? Select all that apply.



Correct

Correct
Correct
Question 6

Which role is responsible for assisting team members to clear obstacles and unblock their work?



Correct
Question 7

What does the Scrum Team reflect on during a Sprint Retrospective? Select all that apply.



Correct
Correct
Correct
Question 8

What’s the overall goal of a burndown chart?



Correct
Question 9

How would you best compare a Kanban board to a Scrum board?



Correct
Question 10

As a Product Owner, you need to organize and visualize your Backlog. What is an example of a tool that would make this task easier?